Location:
South Downs National Park
Client:
Southern Water
Scope of works:
Rising Main Replacement
Delivering essential wastewater upgrades in a highly sensitive environmental setting.
of ageing rising main replaced with new 180mm SDR11 PE pipe to improve long-term network resilience.
intervals between HDD launch and reception pits, reducing excavation and surface disruption.
of tanker operations required during changeover, minimising disruption to residents and road users.
Southern Water appointed Browne to replace 550m of ageing 150mm wastewater rising main at Barnetts Bridge after the asset reached the end of its operational life.
Situated within the South Downs National Park, the scheme presented a unique combination of engineering and environmental challenges. The pipeline route passed beneath a river, alongside ancient woodland, under a public highway and through areas of ecological significance, including sections designated as a Planted Ancient Woodland Site (PAWS).
To deliver the replacement while protecting the surrounding environment and minimising impact on the local community, Browne combined traditional open-cut trenching with Horizontal Directional Drilling (HDD). This trenchless approach enabled the installation of a new 180mm SDR11 PE rising main beneath roads and environmentally sensitive areas with significantly less excavation than conventional construction methods.
The result was a resilient new wastewater asset delivered with minimal disruption to residents, reduced waste generation and extensive environmental protection measures throughout the works.
Protecting a Sensitive Natural Habitat
The project was delivered adjacent to ancient woodland containing a diverse mix of broadleaf and coniferous species, including mature and overmature trees. To safeguard these sensitive habitats, Browne adopted a phased approach to construction, reducing disturbance to root protection zones and limiting impacts on the surrounding ecosystem. Regular environmental inspections and ecological checks ensured that protected habitats remained at the forefront of decision-making throughout delivery.
Delivering Complex Trenchless Installation
Installing a new rising main through challenging ground conditions required careful engineering and planning. Browne utilised HDD to navigate beneath key obstacles along the route, including a river crossing and sections of environmentally sensitive terrain. The trenchless operation required specialist temporary works, launch and reception pits, and close coordination between construction teams to ensure the new pipeline could be installed safely and accurately.
Enhancing Wastewater Network Resilience Across Buckinghamshire
Delivering long-term environmental protection across the River Misbourne catchment
Renewing Critical Wastewater Infrastructure in Bibury
Delivering vital wastewater upgrades in one of Britain's most popular and picturesque villages
Interested in our projects? Explore more of our work.
See all case studies